Total Engineering Solitions About UsMarineHighwaysRailwaysEngineeringFoundryCorrosion ProtectionPartners and LinksContact Us
 

Back to Railways Case Studies
 
 
 
Royal Albert Bridge – Strengthening of Rail Bridge.
Date: 01/12/2002
Company: Taylor and Sons Ltd
     






Taylor and Sons Ltd completed the Strengthening and Painting of this Rail over Water Bridge in December 2002.

The project comprised of sequential repairs and painting over two 60-hour possessions, one being Christmas day and Boxing Day requiring approx 70 tradesmen on rotating 12 hour shift pattern.

Taylor and Sons Ltd carried out the complete supply, manufacture, painting and installation of the metal work with Mowlem rail carrying out the P-way work


Client:
The Main Contractor was Mowlem, the client was Network Rail.