Moorswater and Clinnick Viaducts – Refurbishment of Rail Bridge.
Date: 01/11/2004
Company: Taylor and Sons Ltd
|
| |
|
|
|
Taylor and Sons Ltd are in production on this major project with programmed completion early 2005.
The project comprises of the dismantling and replacement of cast iron balustrading to two large viaducts in Cornwall.
Taylor and Sons Ltd will carry out the complete supply, manufacture, painting and installation.
Client:
The Main Contractor is BirseRail, the client is Network Rail. |
|
|
|
|
|
|
|