Total Engineering Solitions About UsMarineHighwaysRailwaysEngineeringFoundryCorrosion ProtectionPartners and LinksContact Us
 

Back to Corrosion Protection Case Studies
 
 
 
River Mardle Viaduct
Date: 10/03/2005
Company: Taylor and Sons Ltd
     




A project completed for the highways agency under the management of Parsons Brinkahoff.

The structure required major strengthening and painting. The specification was to flash blast and paint using an approved highways specification on the external of the bridge.

We also undertook and Internal paint system on the box girders of the bridge, the specification was an water based expoxy system.


Client:
Main contractor Mowlems Civil Engineering completed April 2004